Case Studies: A23 Beira Interior, Portugal

From BENEFIT Wiki
Revision as of 13:50, 27 March 2015 by Nimda (Talk | contribs)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search
Project Overview
A23a.png
Figure 1: A22 – Algarve, Portugal
A 23 – Beira Interior (E 802 / E 806), Portugal
Contract Duration: 30 years
Budget
NPV for State payments : EUR 654 M
State: EUR 2,279 M
Construction: EUR 590 M
Concessionaire: EUR 1,203 M (Investment, operation and maintenance)
Financing cost:

EUR 823 M

(Financial data from the Court of Auditors report of 2003)
Project Time Line
Call for Tender: October 1997
Date Contract Approved (signed): 13 September 1999
Other important dates for the project:
Completion of Construction: 27 July 2003