Revision as of 09:22, 27 March 2015

</td></tr>
A22 – Algarve, Portugal
Contract Duration:

30 years

Project Overview
A22a.png
Figure 1: A22 – Algarve, Portugal
NPV for State payments: 215.7M (original proposal with 9.5% discount)
State: EUR 1086.6M
Construction: EUR 218.2M
Concessionaire: EUR 472.1M (Investment, operation and maintenance
Budget
Project Time Line
Tender Call: October 1997
Date Contract Approved (signed): 11 May 2000
Other important dates for the project:
Completion of Construction: 11 March 2003
End of Renegotiations: December 2011 December 2011